Federal Highway Administration
|
| 20. | National Tunnel Inspection Standards | Red | |
| Popular Title:Tunnel Inspection |
| RIN 2125-AF24 |
| Stage: Final Rule |
| Previous Stage:ANPRM: Publication Date 11/18/08; End of Comment Period 2/17/09. NPRM: Publication Date 7/22/2010; End of Comment Period 09/20/2010. |
| Abstract: This rulemaking would revise 23 CFR Part 650 -- Bridges, Structures, and Hydraulics, by adding the National Tunnel Inspection Standards (NTIS) under Subpart E. We anticipate that the NTIS may be modeled after the existing National Bridge Inspection Standards and may include requirements for, among other things, inspection procedures, the qualifications and training of inspectors, and a National Tunnel Inventory. |
Effects: |
| Prompting action:None |
| |
| Rulemaking Project Initiated: 01/30/2008 |
Dates for Final Rule: | Milestone | Originally Scheduled Date | New Projected Date | Actual Date | | To OST | 05/31/2011 | 09/14/2011 | 09/13/2011 | | To OMB | 07/01/2011 | 12/29/2011 | | | OMB Clearance | 10/03/2011 | 03/29/2012 | | | Publication Date | 10/14/2011 | 04/05/2012 | | |
| Explanation for any delay: | Additional coordination necessary | |
| Federal Register Citation for Final Rule: None |
Federal Highway Administration
|
| 21. | Lane Line Retroreflectivity | Red | |
| Popular Title:Lane Retroreflectivity |
| RIN 2125-AF34 |
| Stage: SNPRM |
| Previous Stage:NPRM: Publication Date 4/22/2010; End of Comment Period 8/20/2010. |
| Abstract: This rulemaking would amend the Manual on Uniform Traffic Control Devices, incorporated by reference in 23 CFR part 655, subpart F, to include standards, guidance, options, and supporting information relating to maintaining minimum levels of retroreflectivity for pavement markings on all roads open to public travel. We originally scheduled publication of a final rule for 12/30/2011. |
Effects: |
| Prompting action:Statute |
| |
| Rulemaking Project Initiated: 12/07/2009 |
Dates for SNPRM: | Milestone | Originally Scheduled Date | New Projected Date | Actual Date | | To OST | 01/06/2012 | | | | To OMB | 02/06/2012 | | | | OMB Clearance | 05/07/2012 | | | | Publication Date | 05/14/2012 | | | | End of Comment Period | 07/14/2012 | | | |
| Explanation for any delay: | Additional coordination necessary | |
| Federal Register Citation for SNPRM: None |
Federal Highway Administration
|
| 22. | National Standards for Traffic Control Devices; the Manual on Uniform Traffic Control Devices for Streets and Highways; Engineering Judgments (RRR) | Red | |
| Popular Title:MUTCD Engineering Judgment (RRR) |
| RIN 2125-AF41 |
| Stage: NPRM |
| Previous Stage:None. |
| Abstract: This rulemaking would propose changes to the Manual on Uniform Traffic Control Devices (MUTCD) to clarify the definition of "Standard Statements" in the MUTCD and to clarify the use of engineering judgment and studies in the application of traffic control devices. |
Effects: |
| Prompting action:2011 Retrospective Regulatory Review |
| |
| Rulemaking Project Initiated: 12/03/2010 |
Dates for NPRM: | Milestone | Originally Scheduled Date | New Projected Date | Actual Date | | To OST | 02/14/2011 | 03/31/2011 | 03/31/2011 | | To OMB | 03/14/2011 | 05/01/2011 | 05/17/2011 | | OMB Clearance | 06/14/2011 | 08/17/2011 | 07/22/2011 | | Publication Date | 06/20/2011 | 08/24/2011 | 08/02/2011 | | End of Comment Period | 08/22/2011 | 10/24/2011 | 10/03/2011 | |
| Explanation for any delay: | Additional coordination necessary | |
| Federal Register Citation for NPRM: 76 FR 46214 |
Federal Highway Administration
|
| 23. | National Standards for Traffic Control Devices; the Manual on Uniform Traffic Control Devices for Streets and Highways; Compliance Dates Revision (RRR) | Green | |
| Popular Title:MUTCD Compliance Dates (RRR) |
| RIN 2125-AF43 |
| Stage: NPRM |
| Previous Stage:None. |
| Abstract: This rulemaking would revise the Manual on Uniform Traffic Control Devices (MUTCD) to revise the compliance dates for certain requirements in the MUTCD. |
Effects: |
| Prompting action:2011 Retrospective Regulatory Review |
| |
| Rulemaking Project Initiated: 01/20/2011 |
Dates for NPRM: | Milestone | Originally Scheduled Date | New Projected Date | Actual Date | | To OST | 04/01/2011 | | 04/18/2011 | | To OMB | 05/02/2011 | 05/02/2011 | 05/12/2011 | | OMB Clearance | 07/29/2011 | 07/29/2011 | 08/16/2011 | | Publication Date | 08/03/2011 | 08/05/2011 | 08/31/2011 | | End of Comment Period | 08/17/2011 | 10/05/2011 | 10/31/2011 | |
| Explanation for any delay: | N/A | |
| Federal Register Citation for NPRM: 76 FR 54156 |